California Bullet Train Suffers From a “Number of Miscalculations”

This is an artist's conception. It will be a very long time before California has anything more than that.California High-Speed Rail Authority

Fight disinformation. Get a daily recap of the facts that matter. Sign up for the free Mother Jones newsletter.

The LA Times reports today about a minor little cost overrun on the California bullet train. Over the course of five years, the cost of utility relocations along a short section of track near Fresno increased nearly 6x, from $69 million to $396 million:

The California High-Speed Rail Authority board on Friday took up the problem, hearing from its staff that the original estimate contained a number of miscalculations. The number of linear feet of utilities that have to be moved was underestimated, as was the cost per foot for the job, according to a staff memo. Then, there were utilities that nobody even knew were in the ground. The authority changed its mind about some of the work, as well, the report said.

….The history of the utility relocations suggests some turmoil in management decisions — which the rail authority staff said it would not repeat in the future….The staff said that “best management practices,” along with a new database, will enable it to better estimate costs in the future. “Additionally, the assumption that utilities will perform relocations will not be repeated,” the staff memo said.

No worries! This won’t be repeated in the future! I feel relieved.

The California bullet train is obviously one of my bugaboos, and I figure that all bloggers are entitled to one or two. But seriously, reading this stuff makes me wonder if anyone involved in this boondoggle has any experience whatsoever with large construction projects, let alone high-speed rail projects.

POSTSCRIPT: In fairness, I want to note that that this is not, strictly speaking, a new cost overrun. It’s all part of the “worst-case scenario” unveiled in January.

ONE MORE QUICK THING:

Or at least we hope. It’s fall fundraising time, and we’re trying to raise $250,000 to help fund Mother Jones’ journalism during a shorter than normal three-week push.

If you’re reading this, a fundraising pitch at the bottom of an article, you must find our team’s reporting valuable and we hope you’ll consider supporting it with a donation of any amount right now if you can.

It’s really that simple. But if you’d like to read a bit more, our membership lead, Brian Hiatt, has a post for you highlighting some of our newsroom's impressive, impactful work of late—including two big investigations in just one day and covering voting rights the way it needs to be done—that we hope you'll agree is worth supporting.

payment methods

ONE MORE QUICK THING:

Or at least we hope. It’s fall fundraising time, and we’re trying to raise $250,000 to help fund Mother Jones’ journalism during a shorter than normal three-week push.

If you’re reading this, a fundraising pitch at the bottom of an article, you must find our team’s reporting valuable and we hope you’ll consider supporting it with a donation of any amount right now if you can.

It’s really that simple. But if you’d like to read a bit more, our membership lead, Brian Hiatt, has a post for you highlighting some of our newsroom's impressive, impactful work of late—including two big investigations in just one day and covering voting rights the way it needs to be done—that we hope you’ll agree is worth supporting.

payment methods

We Recommend

Latest

Sign up for our free newsletter

Subscribe to the Mother Jones Daily to have our top stories delivered directly to your inbox.

Get our award-winning magazine

Save big on a full year of investigations, ideas, and insights.

Subscribe

Support our journalism

Help Mother Jones' reporters dig deep with a tax-deductible donation.

Donate